Inspection of Air Conditioning Systems under EPBD TM44 (revised)

2012

Available at 20% discount on the CIBSE non member price for IOR members (IOR  price £35 - normal price £40)

The Energy Performance of Buildings Directive (EPBD) was first adopted in 2002. The recast Directive, adopted in May 2010, replaced the original Directive from 1 February 2012 and will be progressively implemented from January 2013. The Directive requires Member States across Europe to put in place 'measures to establish a regular inspection of air conditioning systems of an effective rated output of more than 12 kW'. In the UK separate legislation has been introduced in England and Wales, Scotland and Northern Ireland that requires building owners or managers to undertake regular inspections of air conditioning systems. The regulations and requirements relating to air conditioning system inspections for England and Wales have now been in place for over three years, and for a slightly shorter period for Northern Ireland and Scotland. The principle guidance for the inspections is contained in CIBSE TM44.

CIBSE TM44 is used as the guidance for air conditioning inspections in the UK, the Republic of Ireland, Malta and Gibraltar. The guidance is primarily intended to support inspections which are carried out for compliance with the EPBD, but will also be useful to anyone who wishes to assess the energy effi ciency of an air conditioning system.

With the benefit of the experience gained over the past three years, and to clarify some of the questions about air conditioning system inspections that have arisen over that period, the TM has been revised. The revision also takes into account the reporting templates produced by the Department for Communities and Local Government for the production of reports in England and Wales. These templates will also form the basis for statutory lodgement of air conditioning inspection reports, which will be required in England and Wales as from 6th April 2012 under amendments to the Energy Performance of Buildings Regulations 2007. The revision has also provided the opportunity to incorporate the separate legislative requirements for Northern Ireland and Scotland in the main text of the TM, rather than as separate addenda.

TM44 provides guidance on conducting an air conditioning inspection to satisfy the requirements of the Directive as expressed in the various regulations in the UK. The focus is on systems that use refrigerants to produce cooling. Some of the guidance may also be applicable to elements of other forms of cooling systems, such as those that use pipes or ducts built into the fabric of the building (e.g. cooled deck or ceiling slabs), or those which use aquifers or local water sources to provide cooling solutions.

TM44: 2007 is superseded by this new edition.

In England and Wales the Energy Performance of Buildings (Certificates and Inspections) (England and Wales) Regulations 2007 implement Articles 7-9 of the Directive. They require inspection of all air conditioning systems with rated outputs over 12 kW at intervals not greater than 5 years.For systems over 250 kW they have until January 2009 to complete the first inspections, and for the remaining systems over 12 kW they have until January 2011. 

An Industry Working Group comprising ACRIB, BRE, BSRIA, CIBSE, FETA, HVCA, IoR and Summit Skills has developed this document to give guidance on meeting these regulations which has been published by CIBSE.

Contents includes:

  • 1         Introduction
  • 1.1          Background
  • 1.2          Scope of the inspection required by the EPD Regulations
  • 1.3          Factors affecting air conditioning system efficiency
  • 1.4          Provision of advice
  • 1.5          Preparation for the inspection
  • 1.6          Energy consumption metering
  • 1.7          Extent of the inspection
  • 1.8          Guidance on good practice inspection and maintenance
  • 1.9          Appropriate forms of inspection procedure
  • 2         Inspection of packaged cooling systems
  • 2.1          Checklist of pre-inspection information
  • 2.2          Inspection process for packaged cooling systems
  • 2.3          Reporting
  • 2.4          Inspection checklist
  • 3         Inspection of centralised cooling systems
  • 3.1          Checklist of pre-inspection information
  • 3.2          Inspection process for centralised cooling systems
  • 3.3          Reporting
  • 3.4          Inspection checklists
  • 4         Assessing equipment sizing in relation to the cooling load
  • 4.1          Estimating loads for packaged systems
  • 4.2          Estimating loads for larger installations
  • 4.3          Assessment of cooling capacity
  • 4.4          Assessment of ventilation performance
  • 5         Advice and alternative solutions
  • 5.1          Introduction
  • 5.2          Cooling load reduction
  • 5.3          Alternative cooling techniques
  • 6         Explanatory notes for building owners and managers
  • 6.1          Background
  • 6.2          The inspection process
  • 6.3          The inspection report
  • 6.4          Exchanging information with other inspection or certification procedures
  • 6.5          The scope of the inspection
  • 6.6          Good practice inspection and maintenance of air conditioning equipment
  • References  and suggested reporting format for a packaged cooling system 

 

Members £35.00
Service Engineers £35.00
Non-members £40.00

Add to Basket